Construction of 1,100 MW nuclear power reactor K2 unit in Karachi has been completed by China National Nuclear Corporation, according to media reports. A similar reactor unit K3 will add another 1,100 MW of nuclear power to the grid, bringing the total nuclear power installed capacity of Pakistan to 3,630 MW (12% of total power) by 2022. Hualong One reactors being installed in Pakistan are based on improved Westinghouse AP1000 design which is far safer than Chernobyl and Fukushima plants. In addition, Pakistan is also generating 9,389 MW (about 28% of total power) of low-carbon hydroelectric power in response to rising concerns about climate change.
Karachi Nuclear Power Plant (KANUPP):
With the placement of the outer containment shell, K2 is now ready for containment and heat tests. It is scheduled to begin operations in 2020. It’s built using the Chinese HPR1000 technology, which features a dual containment design, with the outer containment providing additional protection for the primary containment.
![]() |
Karachi Nuclear Power Plant K2 Unit Under Construction. Source: CNNC |
KANUPP is Pakistan's first nuclear power plant where construction started in 1966 in Karachi. The plant was connected to the national grid on 18 October 1972. KANUPP, a pressurized heavy water reactor of 137 MW gross capacity was constructed by Canadian General Electric under a turnkey contract. In 1976, vendor support for spare parts and fuel was withdrawn. The PAEC undertook the task of indigenously manufacturing the required spare parts and nuclear fuel on an emergency basis and, since 1980, KANUPP has successfully operated using fuel manufactured by the PAEC, according to International Atomic Energy Agency (IAEA). Here is an except of IAEA's 2018 report on nuclear power in Pakistan:
"Despite the keen interest of Pakistan in building additional nuclear plants, it took more than two decades before the second nuclear power plant started construction. This delay was due to Pakistan’s lack of access to international nuclear technology coupled with a lack of indigenous industrial infrastructure. The construction of Pakistan’s second nuclear plant, C-1, a pressurized water reactor (PWR), was made possible in 1993 with the help of the China National Nuclear Corporation (CNNC). The plant was connected to the national grid on 13 June 2000 and has a gross capacity of 325 MW. A third nuclear power plant, C-2, with 325 MW gross capacity started commercial operation on 18 May 2011. The fourth unit, C-3, started commercial operation on 6 December 2016. It has a gross capacity of 340 MW and a similar plant, C-4, sited beside C-3, was connected to the grid on 25 June 2017. The first concrete pours to mark the start of construction of Karachi Coastal Power Project, a project containing two nuclear units, K-2 and K-3 (1100 MW each), based on an improved PWR design, were 20 August 2015 and 31 May 2016, respectively."
|
![]() |
Pakistan Among 31 Countries Operating Nuclear Power Plants |
![]() |
New Installed Hydroelectric Power Capacity in 2018. Source: Hydrowo... |
Top 20 Countries by Newly Installed Hydropower Capacity. Source: IHA |
Pakistan Embarks on Construction of Its Largest Nuclear Power Plant
https://www.devdiscourse.com/article/headlines/3210144-pakistan-emb...
Pakistan is constructing its largest nuclear power plant, Chashma Nuclear Power Plant Unit 5, with a capacity of 1200 MWe. The Pakistan Nuclear Regulatory Authority has granted the necessary license. This Chinese-designed Hualong reactor will strengthen Pakistan's energy grid with safe, advanced technological features.
The regulatory approval follows a comprehensive review of safety assessments and operational plans submitted by the Pakistan Atomic Energy Commission earlier this year. This plant will be a third-generation Pressurized Water Reactor of Chinese Hualong design, enhancing energy provision with both active and passive safety features.
With an estimated cost of USD 3.7 billion and a projected lifespan of 60 years, this installation is expected to contribute significantly to Pakistan's grid, joining the already operational Karachi Nuclear Power Plants units 2 and 3.
From Arif Habib Securities:
Power generation in Dec’24 increased by 1% YoY to 7,800 GWh (10,484 MW). However, it remained 2% lower than the reference generation for the month. This brings total power generation for the 1HFY25 to 66,641 GWh (15,091 MW), reflecting a 3% YoY decline. Meanwhile, the cost of power generation fell by 10% YoY to PKR 9.09/KWh, which is also below the reference cost.
The decrease in generation is attributed to lower overall demand due to a drop in temperatures across the country.
https://x.com/arifhabibltd/status/1881308984545554843?s=61
———————-
https://www.brecorder.com/news/40343586
During December, 2,065 GWh of electricity was generated from nuclear, which emerged as Pakistan’s leading source of electricity generation, accounting for 26.5% of the generation mix.
This was followed by hydel, which accounted for 22.8% of the overall generation, ahead of RLNG, which accounted for 20.7 of the power generation share.
Among renewables, electricity generation from wind sources saw a massive uptake, accounting for 3.4% of the generation mix in December 2024, as compared to 1.9% in the same month last year.
Generation from solar, and bagasse amounted to 1%, and 1.3%, respectively, of the generation mix.
World Bank set to approve $1bn loan for Dasu project expansion
https://www.geo.tv/latest/588799-world-bank-set-to-approve-1bn-loan...
Official reveals cost of phase I shot up by 190.1% to Rs1,700bn.
Rise attributed to various factors such including in land acquisition.
After erection of stage II, Dasu project would generate 4,320 MWs.
The World Bank (WB) is set to issue a fresh $1 billion loan for the first phase of the Dasu hydropower project, following the approval of a revised PC-1 with updated completion timelines, The News reported on Monday.
A senior official of the Economic Affairs Division (EAD) revealed that cost of the first stage of the project has shot up by 190.1% to Rs1,700 billion from Rs586 billion.
The increase in the cost is attributed mainly to a delay in land acquisition, security concerns and an increase of US dollar value by 178%.
“The project of stage I would generate 2,160 MWs. However, after erecting stage II of the project, it would generate 4,320 MWs. Dasu Hydropower Project is a run-river project on the Indus River located seven kilometres upstream of Dasu Town, District Kohistan (Upper), Khyber Pakhtunkhwa.
"The site is 74km downstream of the proposed Diamer Bhasha Dam site and 345km from Islamabad. The project will generate 4,320 MWs (12 Units @ 360 MW each) hydroelectric power with annual energy of 21,445 GWh and will be developed in two stages (Stage I and II).
"Stage I will generate 2,160 MW (06 Units @ 360MW each) with annual energy of 12,222 GWh. Stage I will be completed in five years. The WB has already given the loan of $588 million and also extended the guarantee leverage for generating $460 million from the international market.”
However, under the new financing for the project, out of $1 billion, $800 million loan is of International Development Association (IDA) and $200 million will be extended under the International Bank for Reconstruction and Development (IBRD).
Out of the IDA loan, Pakistan will attain $435 million at zero interest rate, $365 million at 5.83% interest rate, and get $200 million under IBRD at 6.13% interest rate.
"We have prepared the revised PC-1 of the project at the cost of Rs1,700 billion and will send it within a couple of days to the Planning Commission for its approval. After that, Water and Power Development Authority (Wapda) and WB will formally sign the $1 billion (loan)," the Ministry of Water Resources confirmed.
The land acquisition for the dam project was to be completed by 2014, but the process finished in 2021-22. Another reason for the escalating cost is the appreciation of US dollar by 178% to Rs278 from Rs100.
"The project was earlier scheduled to get completed by 2023-24 which would now be completed by 2027-28. The Economic Affairs Division has played a pivotal role in diverting the bank’s loan to the project of paramount importance. The WB has already extended $1 billion loan to Pakistan in other heads, but it was not being spent. This is why the loan has been re-purposed and diverted to the Dasu Dam with the approval of the executive board of the bank," added the ministry.
Pakistan Oxygen to Build $4.6M Hydrogen Facility at Port Qasim
https://fuelcellsworks.com/2025/04/22/green-investment/pakistan-oxy...
The company stated the new facility “will strengthen our position in the hydrogen market and provide efficient, reliable gas solutions to key industrial clients.” The project is also expected to play into wider trends of decarbonization and energy diversification as industries seek lower-carbon inputs.
This development adds to the region’s momentum around hydrogen infrastructure. Just 70km away, Oracle Power has been working since 2021 on a proposed 400MW green hydrogen facility in Thatta, Sindh. While a final investment decision has been delayed, Oracle has completed feasibility studies and signed agreements with China Power to move forward with development and operations.
Comment
South Asia Investor Review
Investor Information Blog
Haq's Musings
Riaz Haq's Current Affairs Blog
Pakistan celebrates Earth Day on April 22 every year by organizing various events sponsored by the government and non-government organizations to raise awareness of the issues faced by the earth. Today it is being observed with a range of initiatives, including pledges for zero waste, commitments to sustainable practices, and community-based actions to protect the planet. Pakistan contributes less than 1% of global carbon emissions, but it is among the countries considered most vulnerable to…
ContinuePosted by Riaz Haq on April 22, 2025 at 5:00pm
Pakistan ranks among the top 5 nations in terms of international schools offering schooling based on International Baccalaureate (IB) and IGCSE (Cambridge) curricula. China leads with 1,000 international schools, followed by India (900), UAE (784), Pakistan (598) and Brazil (415). The medium of instruction in these schools is English. …
Posted by Riaz Haq on April 19, 2025 at 8:00am